Upcoming Building Site Construction Work: 7/31 - 8/14

  • Complete demolition of the former library building
  • Commence Vibro Compaction for the 4th & 5th Delray theatre/office building
  • Start foundation work for the 4th & 5th Delray theatre/office building
  • Commence Vibro Compaction for parking garage structure
  • Coordinate relocation of the existing on-site AT&T utility lines
  • Coordinate relocation of the existing on-site gas line

Upcoming Off Site Construction Work: 7/31 - 8/14

  • Engineering/Public works preconstruction meeting
  • 4th Ave land closure/maintenance of Traffic and Signage
  • Start of the Sanitary Sewer relocation 4th Avenue