The next stage of construction for the initial underground garage is the concrete pour. In close
coordination with the City and local law enforcement, a plan is in place to safely secure the site
and surrounding area, temporarily re-route traffic, and execute the pour during the overnight
hours to minimize inconvenience for neighbors, nearby businesses and visitors. (Some noise will
be unavoidable - we apologize in advance.)
For safety, police will be staged at key intersections (Atlantic Ave. at NE 6th Ave. and NE 7th Ave.,
and NE 6th Ave. at NE 1st St.) throughout the period of truck movement. During this time, some
traffic will be re-routed. (See map.)
Timeline:
Friday, Oct. 4:
Mid-day: Preparation begins on-site
8-10:30 pm: Road closures begin
All lanes: NE 7th Ave. between Atlantic Ave. and NE 1st St.
1 lane: NE 6th Ave., south of Atlantic Ave.
Northern parking lot (NE 1st St. at NE 7th Ave.) closed
Saturday, Oct. 5:
12:30 am: Concrete pumps begin staging on NE 6th Ave/Federal Hwy., south of Atlantic Ave
1 am to 1 pm: Concrete pour (Projected start time, estimated 12-hour duration)
1-3 pm: Roads re-open, Normal traffic resumes at NE 6th Ave/Atlantic Ave., NE 7th Ave.